Viaduct: Start work now, final plan later

The state and Seattle officials today said they would move forward this summer with work on portions of the Alaskan Way Viaduct project...

Seattle Times staff reporter

OLYMPIA — The state and Seattle officials today said they would move forward this summer with work on portions of the Alaskan Way Viaduct project, but gave themselves two more years to figure out a final replacement solution.

The agreement comes in the wake of Tuesday's vote that rejected both a tunnel and a new elevated highway along the waterfront.

The plan unveiled today in a noon press conference at Gov. Christine Gregoire's office also includes work to shore up parts of the aging viaduct and increase inspections of the structure.

Engineers have said the viaduct could collapse in a major earthquake.

Gregoire said she wants the state to start dismantling the viaduct by 2012.

"I am determined to take it down before it falls down," she said.

Cost of the repairs and upgrades to start this summer is estimated at $915 million.

The work includes:

• Stabilizing viaduct footings near Washington Street.

• Building a new interchange near Qwest and Safeco fields to help trucks and commuters to move between the waterfront and south downtown.

• Relocating two electrical transmission lines and five feeder lines from the viaduct to Western and First avenues.

• Adding lighting, fire suppression, seismic upgrades and ventilation to the Battery Street tunnel.

advertising

• Strengthening steel structures from Lenora Street to the Battery Street Tunnel.

• Replacing the highway from Holgate Street to Royal Brougham Way.

The announcement was made by Gregoire, Seattle Mayor Greg Nickels and King County Executive Ron Sims.

Gregoire has supported replacing the viaduct with a $2.8 billion elevated highway. Nickels backed a four-lane, $3.4 billion tunnel.

Neither option won a majority of votes in Tuesday's election.

Gregoire said the work announced today would be required regardless of which replacement option is finally chosen.

"We want all of us to come together," she said. "We're on one page today, moving forward."

Gregoire said a final decision on how to replace the central portion of the viaduct must be made within two years, before the state's next biennium budget is approved.

Nickels said he is open to alternatives.

"I will not be advocating a tunnel. I will not be advocating any particular solution," he said.

Copyright © 2007 The Seattle Times Company

Illegal workers quietly let go

Metro won't cut bus service after all

Jerry Large: Food-bank theft turns into a gift

Bumper to Bumper: How can the city let bridges go dark?

NEW - 01:26 AM
Tattoos at Mill Creek church pierce skin, soul

Advertising

Video

Real Salt Lake wins MLS Cup
Real Salt Lake defeated the Los Angeles Galaxy with penalty kicks after 120 minutes of play at Qwest Field in Seattle.

Raw Video | Real Salt Lake receives the MLS Cup trophy
Raw Video | Real Salt Lake fans celebrate
Real Salt Lake fans enter Qwest Field
Raw Video | MLS Cup Opening Ceremony
LA Galaxy's David Beckham
Real Salt Lake's Kyle Beckerman
MLS trophy arrives in Seattle
Chittenden Locks Inspection
Full interview with New Moon actors

Marketplace

nwautos

2009's most fuel-efficient sedansnew
Choosing a new sedan? Weigh the impact of your choice on your wallet and on the planet.
Post a comment

Open Houses

Find this weekend's open house listings.
Or search by location:

Advertising