Originally published Tuesday, July 19, 2005 at 12:00 AM
Hanford plant gets deadline for plan to end construction
Officials with the U.S. Department of Energy at south-central Washington's Hanford nuclear reservation must submit an outline by Sept. 2 for halting work on...
The Associated Press
RICHLAND — Officials with the U.S. Department of Energy at south-central Washington's Hanford nuclear reservation must submit an outline by Sept. 2 for halting work on the massive waste-treatment plant at the site, according to a memo by agency officials in Washington, D.C.
The plant is the federal government's largest construction project, but skyrocketing costs forced the department to announce plans to halt some construction late last month.
The move came as a congressional subcommittee requested an investigation into the rising costs of the plant, which is being built to treat millions of gallons of radioactive waste left from Cold War-era nuclear-weapons production.
The Energy Department's Office of River Protection must submit a comprehensive plan to agency headquarters outlining an orderly halt to construction on the plant.
The plan is due Sept. 2, said Charles Anderson, principal deputy assistant secretary for environmental management, in a memo to Roy Schepens, manager of the Office of River Protection.
The memo also makes clear that any future decisions about key facilities for the plant will be handled in Washington, D.C., rather than at Hanford offices. In addition, all work authorizations and technical directions related to facilities that will handle highly radioactive waste will require Anderson's written approval, the memo said.
Earlier this year, the Energy Department began to study the plant's design and cost estimate after a scientific review found that the force of the ground movements at the plant site during a severe earthquake would be 38 percent greater than previously estimated.
Agency officials have said they are still working on new construction costs in light of those problems. The plant's cost was estimated at $4.35 billion before the contract was awarded in 2000. Already, the cost has grown more than 30 percent — to $5.8 billion.
Congressional leaders have said the new problems could push the estimated cost closer to $10 billion and delays its start by four years.
Under a cleanup pact signed by the Energy Department, U.S. Environmental Protection Agency and Washington state, the waste-treatment plant must be built by 2009 and fully operating by 2011.
UPDATE - 09:46 AM
Exxon Mobil wins ruling in Alaska oil spill case
NEW - 7:51 AM
Longview man says he was tortured with hot knife
Longview man says he was tortured with hot knife
Longview mill spills bleach into Columbia River
NEW - 8:00 AM
More extensive TSA searches in Sea-Tac Airport rattle some travelers
![]()

Entertainment | Top Video | World | Offbeat Video | Sci-Tech
nwautos
Turismo upgrade "Gran Turismo 5: XL Edition" for PlayStation 3 has features such as new car-tuning settings, new NASCAR vehicles, better replay video...
Post a comment
- Lakewood cop accused of embezzling $150K meant for slain officers' families
- 3 big health insurers stockpile $2.4 billion as rates keep rising
- Agency set to investigate handling of 911 call about Josh Powell
- Quick decisions: How Washington hired its new football staff
- Historic day for gay marriage as another fight looms
- Justin Wilcox's versatile defensive style is the right fit for Huskies | Jerry Brewer
- Social worker recounts minutes before Powell fire
- It's Terrence Time: Enigmatic Ross leads Huskies
- $25B settlement reached over foreclosure abuses
- Club promoter convicted in brutal 2010 murder of Des Moines prostitute
- Gay-marriage bill passes House, awaits Gregoire's signature
481 - Historic day for gay marriage as another fight looming
367 - Wanted in Seattle classrooms: more teachers of color
341 - 3 big health insurers stockpile $2.4 billion as rates keep rising
244 - Council members get briefing on arena proposal, minus details
204 - AP Source: Obama to change birth control rule
194 - Oregon live game thread
155 - Pac-12 picks ... including the UW game
140 - Worker: Josh Powell told son he had 'surprise'
108 - Rough road again
98
- Wanted in Seattle classrooms: more teachers of color
- State Medicaid program to stop paying for unneeded ER visits
- 3 big health insurers stockpile $2.4 billion as rates keep rising
- Economy, blogs give survivalists new reason to look to Northwest
- State's share of mortgage settlement: $648 million
- One man's audacious pursuit of sailing history
- Darren Berg gets 18-year sentence for Ponzi scheme
- Bellevue College adds a third bachelor's degree program
- $25B settlement reached over foreclosure abuses
- 'Gauguin and Polynesia': dazzling mix-and-match | Art review