Boeing finds problems with 787 fastener installation
The issue is not the fasteners themselves, but the way they were installed on titanium parts inside the airplane. Some were left sticking up slightly from the titanium surface, leaving a small but technically significant gap between the head of the fastener and the surface.
Seattle Times aerospace reporter
In the middle of the Machinists strike, Boeing inspectors in Everett discovered a new and serious problem with the manufacture of the first 787 Dreamliners.
Boeing admitted Tuesday that about 3 percent of the fasteners installed on the five test airplanes under construction in Everett were installed incorrectly and will have to be removed and reinstalled. Some of Boeing's global partners have found the same problem in airplane sections under construction.
"We are finding that the specification for installation of the fasteners wasn't as clear as it could have been and so it was misinterpreted by folks doing the installation," said Boeing spokeswoman Mary Hanson.
Hanson said the issue was first detected about two weeks ago during an inspection of the "static test" airframe in Everett, an early production airplane that undergoes prolonged stress tests in a large fixture inside the factory. Subsequent inspections found the same problem on the four 787s under final assembly, three of which were due to be flight test airplanes.
The issue is not the fasteners themselves, but the way they were installed on titanium parts inside the airplane. Some were left sticking up slightly from the titanium surface, leaving a small but technically significant gap between the head of the fastener and the surface.
Referring to the incorrectly installed fasteners as "nonconforming" with specifications, Hanson said they were found in various areas of the airplanes, on sections made by various suppliers.
"The locations of the non-conformances aren't isolated to any particular area of the airplane," said Hanson.
She declined to identify which sections or which suppliers are involved. She said a "root cause analysis" is under way to find out why this happened and why it wasn't discovered until so late in the build process.
The first Dreamliner was within a couple of months of its scheduled first flight when the International Association of Machinists (IAM) strike began in September.
"We're going to strengthen our quality management system," said Hanson. "We have already prepared additional training on the installation process that is now being deployed through the factory to our workforce. And we've also sent it to our partners and they are deploying it to all of their workforce as well."
Last year, Boeing cited a shortage of fasteners and the need to insert temporary fasteners as contributing to the earliest delays on the crucial jet program.
Since then, delays have mounted and the first delivery of the airplane was already about 15 months behind schedule before the two-month Machinist strike that just ended. Hanson said Boeing has not determined yet if the discovery of this latest fastener problem, which was first reported online by the trade publication Air Transport World, will add yet more delay or can be fixed during the production recovery that follows the strike.
![]()
Hanson said that Boeing hasn't finalized a revised schedule for the 787.
But Boeing did officially admit Tuesday what has been obvious for some time: that the 787 will not fly this year.
After the previous round of delays, the first test flight had been pushed out to the "third quarter of 2008." But because of the just-ended 58-day IAM strike, that isn't going to happen.
The pushing out of first flight into 2009 is not attributable to the new fastener issue, said Yvonne Leach, another Boeing spokeswoman.
"It's directly related to the duration of the IAM work stoppage," said Leach.
Dominic Gates: 206-464-2963 or dgates@seattletimes.com
Information in the summary of this article, originally published Nov. 4, 2008, was corrected Nov. 5, 2008. A previous version of the summary incorrectly described the fastener installation problem
Copyright © 2008 The Seattle Times Company
RealNetworks makes key play with Rhapsody spinoff
Alaska Air dropping Jones Soda beverages, going back to Coca-Cola
Lots of Buzz over Google latest bid at social networking
Cheaper brands of liquor taste better in tight economy
NEW - 10:04 PM
Dendreon revving up drug plants ahead of FDA decision

nwautos
Associated Press Study: Fatal crashes down in Washington Last year Washington's roads were the scene of the fewest fatal crashes since 1955. According...
Post a comment
nwjobs
Post a comment
Michelle Goodman blogs about work/life balance.
Five reasons to stick with a job you hate -- for now
Post a comment
- Steve Kelley | My treatment of Bedard has been unfair
- Is Washington's tax exemption on bullion a gold mine?
- 747-8 soars smoothly on first outing
- Alaska Air dropping Jones Soda beverages, going back to Coca-Cola
- Super Bowl ads: Betty White, Bud Light, big laughs
- Man found shot dead in pickup truck in Seattle
- Sex, drug rumors swirl about N.Y. Gov. Paterson
- Seattle is first U.S. stop for Picasso exhibit
- Lewis-McChord soldier charged with abusing 4-year-old over alphabet lesson
- Husky Football Blog | Pac-10 expansion to get consideration over next year
- Republicans may be no-shows at health-plan summit
277 - Pac-10 expansion to get consideration over next year
249 - State Senate votes to clear way for tax increases
244 - Lee undergoes foot surgery
230 - Obama: GOP and Dems together can spur job growth
209 - Fort Lewis soldier charged with abusing 4-year-old, holding her head in water
193 - Rivals names Martin one of Pac-10's best recruiters
143 - Belltown boulevard could be completed by early next year
127 - White House mocks Sarah Palin from podium
91 - Bus-tunnel attack while guards watched prompts review of Metro security
81
- Seattle is first U.S. stop for Picasso exhibit
- 747-8 soars smoothly on first outing
- City, Vulcan push higher South Lake Union height limits
- Commentary: Microsoft's creative destruction
- Snap out of your photo funk: How to make sense of all those piles of images
- Wine Adviser | Oregon's quality pinots join the bargain ranks
- Belltown boulevard could be completed by early next year
- Jerry Large | Learning not to copy China
- All You Can Eat | Portage chef Vuong Loc takes Cremant space in Madrona
- Rigorous college-prep classes skyrocketing in Washington state