Originally published July 6, 2007 at 12:00 AM | Page modified July 6, 2007 at 5:52 PM
Dreamliner chief confident of on-time delivery
None of the early problems Boeing encountered with suppliers for its new 787 Dreamliner jet has shaken its confidence that it will smooth...
The Associated Press
SEATTLE — None of the early problems Boeing encountered with suppliers for its new 787 Dreamliner jet has shaken its confidence that it will smooth out production kinks and deliver the plane on schedule, the head of the program said today.
"We've had challenges. You always have challenges when you have a program this complicated going together in what is really kind of record time," Mike Bair told reporters at a briefing two days before the first 787 was scheduled to be unveiled.
"It's stuff we know what to do with," Bair said. "We are expediting a lot of parts right now, and we're going to make sure we get the production system running the way it needs to run."
The 787 that will be displayed on Sunday still has about 1,000 temporary fasteners that must be replaced with permanent ones, and machinists will have to spend several more weeks installing and testing electrical wiring and other systems before the plane is ready to fly, Bair said.
Flight testing on the midsize, long-haul plane is expected to begin in late August or September, he said.
"We don't schedule first flights," Bair said. "The airplane flies when it's ready. To put a firm date on the calendar might make you do something you don't want to do."
The 787, Boeing's first all-new plane since airlines started flying the 777 in 1995, is scheduled to enter commercial service next May, when Japan's All Nippon Airways takes delivery of the first of 50 Dreamliners it has ordered.
To date, Boeing has won 642 orders for the 787, selling out delivery positions through at least 2013, the year rival Airbus expects to roll out its competing A350 XWB.
It will be the world's first commercial jetliner made mostly of carbon-fiber composites, which are lighter and sturdier than aluminum. Boeing has said that and other technological advances will make the 787 more fuel-efficient and cheaper to maintain.
Bair said Boeing isn't worried it will run into the types of delays that have plagued Airbus's A380 superjumbo because it comes down to wiring.
He estimated that the A380 has some 350 miles of wiring — the main source of production problems that forced about two years of delays, slashing billions off its profit forecast for the coming years.
"We're not going to have that problem," Bair said, noting that the 787 has about 60 miles of wiring. The A380 is scheduled to enter commercial service in October.
![]()
Boeing has said it will deliver 112 787s during its first two years of production, with an ultimate goal of having each plane spend just three days in final assembly, compared to 10-14 days for the larger 777, which like Boeing's older jets is made mostly of aluminum.
Because demand for the 787 has exceeded the company's expectations, it is looking at ways to boost production rates, but is not ready to say how much faster those rates will be or when the increase will happen.
"What we're trying to avoid is making a premature decision on rates that would cause a lot of people to build a lot of facilities they might not need," Bair said.
Though it anticipated the problem, an industrywide shortage of airplane fasteners has proved to be one of the stickiest production snags Boeing has encountered so far.
Bair said it will probably take another month or two before the first 787 gets fully fitted with permanent fasteners, and he expects the shortage to remain a problem for six to nine more months.
Copyright © 2007 The Seattle Times Company
Chase shrugs off loss of CD investors
Sunday Buzz: Expedia, Intelius, Classmates slapped by Senate report
Denny Triangle gains skyline, but tenants slow to come
UPDATE - 08:56 PM
Senate Democrats at odds over health care bill
Your Funds: Money for nothing: Some investors pay for advice they never get

Raw Video | Real Salt Lake receives the MLS Cup trophy
Real Salt Lake is handed the 2009 MLS Cup trophy at Qwest Field, November 22, 2009.
nwjobs

Post a comment

Michelle Goodman blogs about work/life balance.
How to tell your office you're gravely ill
Post a comment
nwautos

Choosing a new sedan? Weigh the impact of your choice on your wallet and on the planet.
Post a comment
- 'The Road' takes Viggo Mortensen to Mount St. Helens and Astoria, Ore.
- Craigslist adoption ad: A plea by young mother-to-be? A scam?
- Tugboat sinks on Seattle's waterfront
- Child-support error costs nearly $21,000
- Italian lead prosecutor argues Knox motive was hatred
- Italian prosecutors request life sentence for UW student
- Man shot in chest on E. Union Street in Capitol Hill
- Washington state wines make annual best-of list
- Chase shrugs off loss of CD investors
- Mariners Blog | A Mariners-Tigers swap makes a whole lot of sense for both teams
- Senate vote clears hurdle
239 - Vikings easily beat the Seahawks
128 - Child-support error costs nearly $21,000
121 - Tight Senate vote launches health care over hurdle
120 - Palin excitement builds in Tri-Cities
119 - Cutting through breast-cancer confusion
90 - Game thread
70 - New York terror trials will restore faith in rule of law
56 - Historic health care bill clears Senate hurdle
51 - Chase shrugs off loss of CD investors
50
- Washington state wines make annual best-of list
- Nonprofits get creative using Twitter and Facebook to make donation easier
- It's possible to recover a life lost to hoarding
- Lynnwood is reinventing itself — again
- Great places to cross-country ski for free (or almost) in the Methow
- 'The Road' takes Viggo Mortensen to Mount St. Helens and Astoria, Ore.
- Child-support error costs nearly $21,000
- Recipes: Sesame Pork Roast, Sour Cream Mashed Potatoes, Gingerbread with Lemon Sauce and more
- Banff: powder, peaks & purity
- 175 foster kids in Washington get 'forever families'